Aligned
Conflict
Gap
| Requirement | Texas IBC 2021 w/ amendments |
California CBC 2022 (Title 24) |
Florida FBC 2023 (8th ed.) |
|---|---|---|---|
Corridor Width — Healthcare (I-2) |
8'-0" min Per IBC §407.4.1 |
8'-0" min + 44" clear CBC adds clear width req |
8'-0" min Per FBC §407.4.1 |
Fire-Resistance Rating — Corridor Walls |
1 hour Per IBC §1020.1 |
1 hour Per CBC §1020.1 |
1 hour Per FBC §1020.1 |
Smoke Compartment Area |
22,500 SF max Per IBC §407.5.1 |
22,500 SF + 150' travel CBC adds travel distance limit |
22,500 SF max Per FBC §407.5.1 |
Automatic Sprinkler System |
Required — NFPA 13 All I-2 occupancies |
Required — NFPA 13 All I-2 occupancies |
Required — NFPA 13 All I-2 occupancies |
Wind Load Design |
ASCE 7-22 Standard reference |
ASCE 7-22 Standard reference |
FBC §1609 + HVHZ High Velocity Hurricane Zone overlay |
Seismic Design Category |
SDC A-B (typical) Low seismic risk |
SDC D-F High seismic risk — additional requirements |
SDC A-B (typical) Low seismic risk |
Energy Code Compliance Path |
IECC 2021 / 90.1-2019 Either compliance path |
Title 24 Part 6 CA-specific energy code (stricter) |
IECC 2021 / 90.1-2019 Either compliance path |
| Summary | 6 aligned · 0 conflicts |
3 aligned · 4 conflicts Stricter in most categories |
5 aligned · 1 conflict HVHZ overlay for wind |